| 1. Arrive, brief occupants and assess | - Occupants, children or pets entering work area → trips, contact with exposed parts
- Unexpected site conditions (damaged board, roof access) → work proceeds unsafely
| - ISOBarricade switchboard area and roof access with bollards/tape; agree no-go zone with occupants
- ADMINWalk the site before unloading; confirm scope and switchboard location with homeowner
- ADMINTell occupants when power will be off and for how long
|
| 2. Inspect switchboard backing for asbestosHigh risk work: 5 Asbestos | - Meter panel may contain asbestos (common in pre-1990 SA homes) → inhaling fibres if drilled or broken
| - ELIMDo not drill, cut or break the existing panel; if replacement needed, SA Power Networks / licensed asbestos removalist removes it
- ADMINTreat any black/brown compressed-fibre board as asbestos unless tested CHECK: confirm house age / panel type
- PPEP2 disposable respirator available if panel must be handled
|
| 3. Isolate supply and prove de-energisedHigh risk work: 12 Electrical | - Contact with live parts → electric shock, arc flash, death
- Supply re-energised by others while working
| - ISOIsolate at main switch; arrange SAPN service-fuse withdrawal for board replacement CHECK: confirm SAPN booking
- ISOLock out and tag isolation point; keep the key on you
- ADMINTest-before-touch with a proved voltage tester (prove–test–prove) on every conductor
- PPEInsulating gloves and arc-rated clothing for any testing near live parts
|
| 4. Replace switchboard and fit new circuitHigh risk work: 12 Electrical · 5 Asbestos | - Residual live conductors (consumer mains, solar/battery backfeed) → shock
- Sharp edges, manual handling of new enclosure → cuts, strain
| - ISOIsolate and tag any solar inverter / battery (AC and DC) before opening board CHECK: confirm if solar/battery present
- ENGInsulated tools and shrouding on any conductor that cannot be de-energised
- PPECut-resistant gloves when handling enclosures and cable tray
|
| 5. Work in roof space to run cable | - Heat in roof space (often 45 °C+ in summer) → heat stress
- Falling through ceiling / off ladder → fractures
- Existing live cables, vermin, loose-fill insulation → shock, bites, irritation
| - ADMINSchedule roof-space work before 11 am on hot days
- ENGWalk only on joists; use crawl boards across ceilings; portable LED lighting
- ADMINMaximum 20 minutes in the roof space then a break with water; buddy stays at the manhole
- PPEP2 respirator, long sleeves, gloves, eye protection
|
| 6. Mount outdoor unit bracket at 2.4 m and run conduitHigh risk work: 1 Falls over 2 m | - Fall from ladder while drilling/fixing → head injury, fractures
- Dropped tools/bracket → struck-by injury to people below
| - SUBUse a mobile scaffold or platform ladder rather than a single-stile ladder CHECK: confirm access equipment
- ENGLadder footed on firm level ground, secured at top, 1:4 angle; three points of contact
- ISOExclusion zone below work area; no occupants within 2 m
- ADMINTool lanyards; bracket lifted by second worker, not carried up the ladder
|
| 7. Terminate, test and re-energiseHigh risk work: 12 Electrical | - Incorrect connection → shock or fire on re-energising
- Re-energising while someone is still working
| - ADMINComplete insulation resistance, polarity and earth continuity tests before energising
- ADMINVerbal all-clear from every worker; remove own lock and tag last
- ADMINIssue Certificate of Compliance (CoC) to owner
|
| 8. Clean up and hand over | - Offcuts, dust, open manhole → trips and falls for occupants
| - ADMINRemove all waste and offcuts from site
- ADMINClose manhole, remove barricades last, walk the site with homeowner and explain new board
|